ERECTION METHOD
STACK/CHIMNEY PARIT BARU COAL FIRED
STEAM POWER PLANT PROJECT 2x50 MW
(SITE BENGKAYANG – WEST KALIMANTAN)
Surabaya, 23 February 2016
ERECTION METHOD
CRANE
USING CRANE :
1) Roughter Crane 35 Ton for service crane (Assembly and moving
material
2) Crane 50 Ton for erection Chimney and Stack until elv + .40 meter
3) Crane 250 Ton for erection Chimney and Stack until Top level.
CRANE 50 TON
CRAWLER CRANE 250 TON
ROUGHTER CRANE 35 TON
ERECTION METHOD
Stack & Chimney
PREPARATION LIFTING :
Preparation material in the laydown area, according to stages of
erection that facilitated moving the material to the assembly area.
Assembly material for preparation lifting to the stage of erection.
For Chimney :
Splicing chimney segment for lifting.
For Stack :
Stack assembly in accordance segment lifting
Preparing material already assembly moving to lifting crane area,
alternately between the material and the material chimney stack
LAYDOWN AREA
CONNECTING SEGMENT CHIMNEY
ASSEMBLY AREA STACK & LIFTING AREA
ERECTION METHOD
Stack & Chimney
MATERIAL SUPPORTING :
•
•
•
Temporary Platform required as the access of
workers to perform welding
Temporary Platform installed in time before the
chimney segment erection
Temporary Platform uses material elbow / pipe
as a main frame that is welded to the chimney
walls and wooden planks are used as an access
floor works
Temporary Platform
•
•
•
•
Temporary Ladder
Dismantling temporary platform performed after
welding inspection by the Quality Control
Method release temporary platform by using a
cutting torch and grinding
To help the workers in the process of releasing
temporary platform, we used temporary ladder
which is hanging on a temporary platform on top
During the process of release temporary
platform, the worker must be use safety line
ERECTION METHOD
Stack & Chimney
Temporary Platform
Temporary Ladder
ERECTION METHOD
•
•
•
To facilitate the joint process on the stack need
temporary platform columns and bracing middle
stack
Temporary platform is installed after the column
and horizontal bracing installed
Temporary Platform using scaffolding pipe as
the main frame and planks of wood as a floor to
worker’s stand
Stack & Chimney
ERECTION METHOD
Stack & Chimney
1st SECTION :
Installation the base plate both chimney with orientation on the
direction the flue gas door
Leveling the placement on the base plate design in accordance with
the basis for calculating the difference in the base plate stack (frame)
Install first segment both chimney until level elv + 12 meter with
controlling verticality (theodolite).
Install stack (frame), base until elv + 12 meter
INSTALL CHIMNEY
INSTALL STACK (FRAME)
ERECTION METHOD
Stack & Chimney
2nd SECTION :
Install second segment both chimney until level elv + 22,6 meter
with controlling verticality (theodolite).
Install stack (frame) until elv + 22,6 meter
INSTALL CHIMNEY
INSTALL STACK (FRAME)
ERECTION METHOD
Stack & Chimney
3rd - 8th SECTION :
Install segment third until eight to both chimney from
level + 22,6 meter until level elv + 91,7 meter
installation work done as before by adjusting the
carrying capacity of crane. Always controlling
verticality with theodolite
Install stack (frame) from level + 22,6 meter until level
elv + 91,7 meter
A periodical such as the implementation of the
previous segment
Installation Chimney and Stack done alternately with
a higher precedence than the Chimney Stack heights.
ERECTION METHOD
9th Top Level :
Installation segment
chimney on Top level by
controlling the overall
Verticality from base to
top
Doing the improvements
and fixtures stack
chimney
Doing cleaning stack
and chimney to
prepared BAST
Stack & Chimney