Penawaran 15 NC GMS XI 2019 REV2 PAKET PEKERJAAN PANEL & KABEL DISTRIBUSI

advertisement
PT RAUN KARYA SUKAMEMBAH
Citra Harmoni, Blok I7 – 8, Sidoarjo Tel
081.2100.7689 , 085.3356.0808
[email protected]; [email protected]
www.raunkarya.co.id
NOVEMBER 26, 2019
PT GUNUNG MAS SAMUDRA
Add. Jl. Tambak Osowilangun No.197, Tambak Osowilangun, Kec. Benowo, Surabaya 60191
Attn.: Bpk. Arief Rakhman (HRD & GA)
1. PENAWARAN
No. : 015.NC/GMS/XI/2019/REV-2
2. PROYEK
- PAKET MATERIAL & JASA PANEL DAN KABEL DISTRIBUSI
3. LINGKUP PEKERJAAN: MATERIAL DAN JASA
SESUAI DESKRIPSI PADA NO. 4 PADA PENAWARAN DAN LIST TERLAMPIR
4. HARGA PENAWARAN
No.
Deskripsi
Harga Material dan Jasa (Rp)
A.
SUB TOTAL PEKERJAAN PANEL: 2xMDP
26,500,000
B.
SUB TOTAL PEKERJAAN KABEL POWER
151,500,000
C.
PEKERJAAN LISTRIK KE DEPO & GATE SYSTEM
87,000,000
TOTAL HARGA MATERIAL & JASA
265,000,000
Note:
Ref hasil survey ke-2 tgl 22 Nov’19 dan meeting tambahan 26Nov’19, List Pekerjaan,rincian harga, single line distribusi
terlampir
5. TERMIN PEMBAYARAN
No.
1.
2.
3.
4.
Cara Pembayaran
Uang Muka/Termin I Maks. 7 hari Setelah PO/SPK/Kontrak
Pekerjaan
Progress/Termin II maks. 7 hari Setelah material Panel dan
Kabel Power on site disertai Berita Acara Material on Site
Progress/Termin III maks. 7 hari Setelah progress pekerjaan
70% disertai Berita Acara Progress
Pelunasan/Termin IV Maks. 7 hari Setelah pekerjaan
selesai/Berita Acara Penyelesaian Pekerjaan
Page 1 of 5
Prosentase
30%
30%
30%
10%
PT RAUN KARYA SUKAMEMBAH
Citra Harmoni, Blok I7 – 8, Sidoarjo Tel
081.2100.7689 , 085.3356.0808
[email protected]; [email protected]
www.raunkarya.co.id
Pembayaran menggunakan mata uang IDR (Indonesia Rupiah) tanpa ada pemotongan, melalui rekening dibawah
ini:
Nama Bank
: Bank Mandiri
No. Rekening
: 141-001-648-773-8
Penerima
: PT RAUN KARYA SUKAMEMBAH
Pembayaran dilakukan dengan transfer secara langsung ke rekening bank tersebut tanpa ada pengurangan
(transfer charge, bank charges, dll).
6. JADWAL PENYELESAIAN
“Jadwal Penyelesaian”, adalah sebagai berikut :
Komponen
No. A sampai C
Jadwal
4 minggu setelah termin pembayaran no. 1
diterima
7. PENGECUALIAN
Penawaran belum termasuk PPN, TIDAK TERMASUK: pekerjaan sipil & struktur, ijin-ijin yang diperlukan,
penyediaan listrik dan air kerja, pekerjaan lain yang jenis dan jumlahnya tidak disebutkan dalam penawaran ini,
pekerjaan tambah berlaku apabila jumlah pemasangan/spek material bertambah/ada perubahan sesuai
permintaan client/user.
8. MASA BERLAKU PENAWARAN
Penawaran ini berlaku untuk 1 (satu) minggu dari tanggal penawaran dan akan divalidasi (jika perlu).
9. GARANSI (WARRANTY)
3 (tiga) bulan garansi pekerjaan sejak penyelesaian pekerjaan di site proyek dan tidak disebabkan kerusakan
oleh pihak lain
10. HUKUM YANG MENGATUR, TEMPAT YURIDIKSI
Penawaran dan kewajiban yang di identifikasikan disini diatur oleh Hukum Negara Indonesia. Semua perselisihan
yang timbul dari atau sehubungan dengan penawaran diselesaikan sesuai dengan persyaratan dan ketentuan dalam
penawaran ini.
PT RAUN KARYA SUKAMEMBAH
Ni Luh Putu Chandra Dewi
Director
Page 2 of 5
PT RAUN KARYA SUKAMEMBAH
Citra Harmoni, Blok I7 – 8, Sidoarjo Tel
081.2100.7689 , 085.3356.0808
[email protected]; [email protected]
www.raunkarya.co.id
LIST PEKERJAAN_PAKET MATERIAL & JASA PANEL DAN KABEL DISTRIBUSI
REV
02
No.
Qty
Unit
1
set
14,500,000
1
set
12,000,000
600
5
2
mtr
set
set
83,000,000
1
1
1
1
lot
lot
lot
lot
21,000,000
3,000,000
3,000,000
13,000,000
17,000,000
11,500,000
2
set
10,000,000
11 Kabel Twisted AL (RSTN) 4 x 16mm (Supreme/Eterna) dan instalasi ke Depo
100
mtr
7,000,000
12 Kabel Twisted AL (RSTN) 4 x 16mm (Supreme/Eterna) dan instalasi ke Gate
Item
A. PEKERJAAN PANEL
1 Main Distribution Panel
(MDP 1)
Deskripsi
Main CB 100A, 3phase, 3 pole tipe outdoor, 1 incoming, 2
outgoing terdiri dari
Harga (Material &
Jasa)
Local Box Panel W60 x H80 x D20, standar finishing, mounting bracket
MCCB Schneider 3 Phase 100 A x 1 pcs
MCCB Schneider 3 Phase 50 A x 2 pcs
MCB Schneider 1 Phase 10 A x 3 pcs
Indikator & Aksesoris
CTs, Ammeter, Vmeter, Vselect, Pilot lamps, fuses,
internal wiring & busbars Cu, gland, duct, rail
termasuk pemasangan di site, aksesoris untuk setting, levelling, dokumen wiring
diagram
2
Main Distribution Panel
(MDP2) & SDP 4, 5
Main CB 100A, 3phase, 3 pole tipe outdoor, 1 incoming, 3
outgoing terdiri dari
Local Box Panel W60 x H80 x D20, standar finishing, mounting bracket
MCCB Schneider 3 Phase 100 A x 1 pcs
MCCB Schneider 3 Phase 50 A x 1 pcs
MCB Schneider 3 Phase 20 A x 2 pcs
MCB Schneider 1 Phase 10 A x 3 pcs
Indikator & Aksesoris
CTs, Ammeter, Vmeter, Vselect, Pilot lamps, fuses,
internal wiring & busbars Cu, gland, duct, rail
termasuk pemasangan di site, aksesoris untuk setting, levelling, dokumen wiring
diagram
B. PEKERJAAN KABEL POWER
3 Kabel Twisted AL (RSTN) 2 x 4c x 50mm (Supreme/Eterna) & instalasi
4
5
6
7
8
9
Tiang Listrik
Grounding panel
9 M di atas tanah, 2 M cor bawah tanah & instalasi
2 titik dengan BC 50
Conduit
Pipa PVC 1.5", clamps, elbows, joints, galian & instalasi
Terminasi/Koneksi
untuk semua kabel power pada point 4 s/d 9
Support/Hangers
Support/hangers conduit, pipa dll
Aksesories, material bantu Cable ties, schoen/pin/lugs, vinyl, electrical dop, electrical
& alat bantu
tape, marking, dll
C. PEKERJAAN LISTRIK KE DEPO & GATE SYSTEM
10 Tiang Listrik
9 M di atas tanah, 2 M cor bawah tanah, instalasi, dan
junction box panel
300
mtr
20,500,000
50
mtr
16,500,000
13
4 x 16mm (Supreme/Eterna), instalasi, galian dan
perapihan
14 Kabel NYA (Grounding)
2 x 16mm (Supreme/Eterna) & instalasi
450
mtr
16,500,000
15 Conduit
Pipa PVC 1.5", clamps, elbows, joints, galian & instalasi
1
2
lot
set
3,500,000
7,000,000
1
lot
6,000,000
Kabel NYFGbY (RSTN)
Panel junction
16
1x MCB 50A, 3ph; 6x MCB 16A, 1 ph; 3x MCB 10A, 1 ph:
pilot lamp RST
Aksesories, material bantu Cable ties, schoen/pin/lugs, vinyl, electrical dop, electrical
17 & alat bantu
tape, marking, dll
TOTAL HARGA MATERIAL & JASA
Page 3 of 5
265,000,000
PT RAUN KARYA SUKAMEMBAH
Citra Harmoni, Blok I7 – 8, Sidoarjo Tel
081.2100.7689 , 085.3356.0808
[email protected]; [email protected]
www.raunkarya.co.id
SINGLE LINE DISTRIBUSI
Future
SDP3
untuk
panel
plug-in
reefer
Future
SDP1
untuk
panel
plug-in
reefer
Page 4 of 5
Future
SDP2
untuk
panel
plug-in
reefer
PT RAUN KARYA SUKAMEMBAH
Citra Harmoni, Blok I7 – 8, Sidoarjo Tel
081.2100.7689 , 085.3356.0808
[email protected]; [email protected]
www.raunkarya.co.id
LAYOUT PLOTTING EQUIPMENT
POSISI Junction
Panel 2 - Gate
POSISI MDP 2
dekat PJU6
POSISI MDP 1
dekat PJU4
POSISI Junction
Panel 1 - Depo
POSISI LVMDP Existing
– Ruang Genset
POSISI PJU1
Page 5 of 5